We offer professional inspections and tests (revisions) of
lifting equipment within the scope of our company's authorization in
accordance with the Decree No. 508/2009 Coll:
- Aa - crane and hoist with motor drive, e.g. electric, hydraulic, with a
lifting capacity exceeding 1 000 kg and crane and hoist with human drive
exceeding 5 000 kg, including permanent crane runway and temporary crane
runway of the jib type,
- Ab - a power-driven mobile work platform with a lifting height of over
1,5
m,
- Ac1 - a lift and a lifting platform which is a permanent part of the
building and the premises, namely a passenger and freight lift with
permitted passenger transport,
- Ac2 - lift and lifting platform which is a permanent part of the
building
and the premises, namely a goods lift with access for persons to a cage,
- Ac3 - a lift and lifting platform which is a permanent part of the
building
and the premises, namely a goods lift with restricted access for the
carriage of persons,
- Ac4 - a lift and lifting platform which is a permanent part of the
building
and the premises, namely a lifting platform with the transport of
persons
and cargo permitted,
- Ad1 - a construction lift for the transport of persons and cargo,
- Ad2 - a construction lift for freight with access for persons to the
supporting platform,
- Ae - rack stacker with operator's station on the stacker and its
transfer
station,
- Af - escalators and walkways,
- Aj1 - a movable motorized stage device in the upper stage section, such
as a
stage thrust, fire and acoustic curtain, portal bridge and portal tower,
lighting battery, hanging lamps and chandeliers, projection frame,
- Aj2 - a movable motorized stage device in the lower stage section, for
example, lift table, orchestra table, stage trap,
- Ba1 - a power-driven crane and hoist with a lifting capacity of up to
and
including 1 000 kg and a human-powered hoist with a lifting capacity of
1
000 kg up to and including 5 000 kg,
- Ba2 - power-operated gantry for lifting loads,
- Bb - lifting gear of a power-driven transport trolley and loader
designed
for lifting and transporting a load by means of a means of tying,
hanging or
gripping,
- Bc2 - an additional lifting accessory for the suspension or gripping of
a
load which is not a permanent part of the technical lifting equipment of
Group A and Group B, namely a device for suspension or gripping of a
load,
for example a magnet, a traverse, a suction device, a tong, a grab,
except
for the means referred to in Group C(a),
- Bd1 - a special power-driven lifting device designed to lift a load,
namely
a lifting ramp,
- Bd2 - a special lifting device with a motor drive designed for lifting
loads, namely a lifting platform,
- Bd3 - a special power-driven lifting device designed for lifting a load,
namely a stable, mobile and relocatable service lifting device which is
designed for lifting a vehicle only,
- Bd4 - a special power-driven lifting device designed for lifting a load,
namely a lifting head designed to be mounted on or in a vehicle and
intended
for loading or unloading a load,
- Be - a freight construction lift without access for persons to the
supporting platform,
- Bf - a power-operated vertical sliding gate with a lifting height of
more
than 2,7 m,
- Bg - a rack stacker without an operator's station on the stacker and its
transfer unit, except for equipment which is part of automated handling
and
storage systems,
- Bh - human-powered stage equipment,
Bi - stair lift and vertical lifting platform designed for use by a
person
with reduced mobility.
Group C technical equipment:
- Ca - a means for tying and suspending a load that is not a permanent
part of
the lifting device, e.g., a lanyard, chain, strap, belt, hook, shackle,
- Cb - a technical lifting device which is part of a working means, such
as a
process line, machine or automated handling and storage system,
- Cc - technical lifting equipment assembled on a one-off basis, e.g. for
assembly purposes, for transport,
- Cd - other technical lifting equipment of group B with human power.